Oil & Gas NewsFriday, 11 December 2009 HS&E in Design: An Approach for RussiaBackground Earlier work by the Tyumen Task Force (TTF) in 1992/3 identified the importance of re-establishing a Health, Safety and Environment (HS&E) culture in the prolific oil and gas operations of Western Siberia with the idea of developing and modernising oilfields within the flood plain of the Ob river and its tributaries. TTF conducted field surveys and assessment studies in order to scope the content and location of model oil and gas field developments in the Region, in addition to providing loans to qualifying production associations for the following activities:
Qualification included the drawing up of plans to:
Objectives of this Article The objective of this article is to draw on this earlier TTF experience in Western Siberia and to outline how the timely and effective use of Hazard Identification (HAZID), Value Engineering and Risk Assessment studies in the design process can be central to establishing sustainable development and operating practices for oil and gas projects in the Region. The article aims to show the potential for the following:
This article lists the streams in the HS&E in Design process and gives examples where the above studies have been successful in locations bordering Russia as well as in Russia itself. The example for the HAZID Study is taken from a major infrastructure project in Italy. For this project, latent hazards in the onshore natural environment are identified and analysed. HS&E in Design is incorporated into projects in five parallel streams:
The scope of work represented by these streams is then applied to produce deliverables at key milestones in the project lifecycle:
![]() Front End Engineering Design (FEED) corresponds with the preparation of the technical and economic basis, is completed during the system definition phase of a project, and at a point agreed with the Client. Hazard Identification, Risk Assessment and Value Engineering HAZID Studies are held as early as Concept selection when the hazard profiles of development options are compared. They are refined in successive project phases to meet defined quality levels. The HAZID is concerned with potential major accident hazards, which as a minimum can be defined as:
Also the identification of the safety and environmental critical elements that are required to arrest a major hazard developing into a major accident or incident. HAZOP Studies are scheduled for Concept definition and Detail design. The objective of a HAZOP can be summarised:
Quantitative Risk Assessment is used to enumerate risk levels to persons, the environment and investment, chiefly for comparison with corporate and regulatory acceptance criteria. For each potential major accident hazard, which qualifies for QRA, the frequency of its occurrence is calculated from Industry data and using fault tree analysis. The consequences of the unfolding accident or incident are then evaluated via event trees using impairment data and rule sets. For a successful development, QRA is used to demonstrate that the residual risk levels to working groups, the average individual or to society as a result of a petroleum development or an oil and gas field operation are as low as reasonably practicable (ALARP). ALARP statements are first developed during the concept selection process and are refined through the project lifecycle. ![]() Verification activities ensure that safety and environment critical elements identified during HAZID and HAZOP and evaluated in QRA are suitable and sufficient and can and do continue to meet the Performance Standards required of them in their role of safeguarding against potential major accident hazards. Performance Standards specify the requirements for: Functionality; Availability; Survivability; and Interaction with other safety critical systems. Value Engineering Workshops are used as part of the concept selection process and at the close of the concept definition phase to analyse the primary functions of the project, with a view to attaining the lowest lifecycle costs without compromising safety, schedule or client goals and targets. A multi disciplinary team including project and client personnel is led by an experienced facilitator to identify and study alternatives such as:
through following a Value Engineering process as outlined in the figure below. ![]() Example Studies A) GALSI Project: Hazard Identification Study The table opposite is an extract from the Hazard Register created interactively during the Concept definition phase HAZID for the GALSI Project. The table provides details of the Natural Environment Hazards with the potential to impact the onshore section of a major gas pipeline. A later HAZID, which is scheduled for Detail Design will:
B) Ukraine Gas Field and CPFs: HAZOP Studies A programme of Hazard and Operability (HAZOP) studies for the revamp and modernisation of gas fields and Central Processing Facilities (CPF) in the Ukraine enabled actions to be identified and taken to systematically review, and where required upgrade, the system of process safeguards and operating procedures for these facilities. Process units that were subject to HAZOP included wellheads and wellpad manifolding, product storage and truck loading facilities and tie-ins to existing export pipelines and central processing facilities. Some facilities were designed to be operated manually and other larger facilities via Distributed Control Systems (DCS). HP/LP interfaces were identified and safeguarding options identified to permit the production of new, more productive wells through existing facilities. Tie-ins to existing facilities were analysed to ensure that facilities engineered to different codes and standards could be connected and integrated safely. For field shutdown valves and plant pressure safety valves, outline Failure Modes and Effect Analyses (FMEAS) were carried out by the HAZOP Team in order to fully understand the performance of the device during an upset condition. An overall system of nodes was designed to provide the ability to compare the findings of the HAZOP Study for a manually operated CPF with its automated counterpart. Cause and Effect Charts were compared and analysed and recommendations were made for subsequent studies aimed at determining the required Safety Integrity Level (SIL) of safety instrumented systems. ![]() C) Sakhalin II: Risk Assessment of Deferred Hydrotesting The pipelines' pre-commissioning plan for the Sakhalin Phase II development called for each pipeline section to be flooded with treated water, cleaned, gauged and hydrotested immediately after pipelay during the ice free period of the year. This required review, as disposal of this treated water was out to sea and licenses were not forthcoming. A risk assessment was commissioned to analyse and identify risk reduction measures for an alternative pre-commissioning strategy where the pipeline sections installed in the ice free period would be left air filled during the ice season, awaiting completion the following summer. This air-filled period could last as long as 16 - 18 months. A key corrosion risk reduction measure was to vacuum dry the pipelines after installation, leak test and then pack them with Nitrogen to 0.35 bar. The benefit of this risk reduction measure can be seen in the chart below in terms of how the residual risk is driven to the left. D) Shah Deniz: Shipping Risk Assessment A QRA was performed for the near shore sections of oil, gas and condensate pipelines in order to evaluate the hazards posed by shipping in Sangachal Bay:
Justifiable expenditures for eliminating these hazards were calculated based upon the estimated annual damage frequencies and the lifetime damage costs due to these hazards. Effective risk reduction measures for each hazard were identified and costed. Analysis showed that the risks associated with ship grounding determined the cost effective water depth to which pipeline trenching and backfill should be provided. The original near shore approach specification stated that pipelines were to be trenched and backfilled to the 11m water depth. QRA showed that the water depth up to which this protection could be justified could be reduced to 8.4m. The near shore shelf has a very gradual slope in this area of the Caspian Sea; thus the QRA enabled some significant and justifiable cost savings to be made. With this risk reduction measure in place, as well as the steps of:
These being in place, residual risks to these hydrocarbon pipelines due to shipping hazards in Sangachal Bay were demonstrated to be as low as reasonably practicable (ALARP). The justifiable spend to protect the pipelines from a sinking ship was shown to be significantly below the cost of implementing additional risk reduction measures. ![]() E) Shtokman Development: Verification Scheme A Verification Scheme was prepared for the Safety Critical Elements identified as being suitable and sufficient safeguards to prevent, detect, control, mitigate and enable recovery from potential major accident hazards identified during the FEED HAZID for the onshore and offshore sections of the Shtokman trunklines. Each Safety Critical element has a performance standard associated with it, which provides engineering details regarding the following:
For each Safety and Environmental Critical Element, the Verification Scheme details the independent assurance and examination activities required to assure and verify that the performance standard can be evaluated and attained during:
The Verification Scheme also provides a means of controlling any subsequent addition to or modification of the safety critical system. F) Republic of Korea: EPC Value Engineering Workshop Details are confidential, however, Critical Success Factors for a major refinery revamp and modernisation project were agreed with the managing contractor to include:
An analysis of the Primary EPIC Functions led by the workshop facilitation team as shown in the figure below identified opportunities which were still achievable at the close of FEED to:
Some other value improving practices could not be incorporated into this project due to time pressures, but remained available as best practices for incorporation in similar future projects. ![]() Conclusions and Summing up This article has discussed the potential of effective hazard management and value engineering programmes in the design process to make a positive impact to oil and gas field developments in the challenging natural, working and business environment of Russia. A map of the Hazard Management Process is shown below, which shows the role and position of HAZID, HAZOP and QRA in the process. A key component of the ALARP Assessment is the verification that the safety critical elements are suitable and sufficient and will remain as such through the project lifecycle. Any practices and processes adopted by the project from a Value Engineering workshop are then subjected to HAZID and HAZOP. Topical examples have been used to highlight the possibilities that these studies and workshop can have, particularly when regional knowledge and project experience are considered.
posted by The Rogtec Team @ 17:05
|
Latest News:
|
|
ROGTEC Magazine © 2007/ - All rights Reserved | Legal Disclaimer Website design and development by DTimagen - Web marketing and SEO by Solar Internet |
|
0 Comments:
Post a Comment
<< Home