PetroNeft Resources: Third successful well drilled at South Arbuzovskoye
PetroNeft (AIM: PTR) an oil & gas exploration and production company, operating in the Tomsk Oblast, Russian Federation, and 50% owner and operator of Licences 61 and 67, is pleased to announce the completion of a successful three well initial development programme on the southern extension of Arbuzovskoye in Licence 61 and the addition of a fourth well based on the positive results.
Highlights
Third successful well drilled at South Arbuzovskoye
Fourth well added as follow-up
Record production achieved
Production
- Current gross production from Licence 61 increased to about 3,500 bopd (1,750 bopd net to PetroNeft).
- Increase due to three strongly performing new wells at Arbuzovskoye.
- This is the all-time record high production for the Licence area.
Arbuzovskoye Well A-213 – Vertical Production Well
- Initial well discovered oil for the first time in the secondary J1-2 interval at Arbuzovskoye.
- Perforations have now been added to the J1-1 interval.
- The combined production from the J1-1 and J1-2 intervals is greater than 350 bopd.
Arbuzovskoye Well A-214 – Horizontal Production Well
- Initial horizontal well with record 931 m net pay.
- Current rate of production in excess of 750 bopd with 5 % water.
Arbuzovskoye Well A-215 – Horizontal Production Well
- Recently completed horizontal well with 809 m net pay.
- Current rate of production is 650 bopd with 5 % water.
Arbuzovskoye Well A-216 – New Deviated Production Well
- New well added to programme based on results of initial three wells.
- Spudded on 20 June 2016
- Results anticipated later this month.
Sibkrayevskoye Well S-374 – Vertical Delineation Well
- Spudded on 3 July.
- Results expected in August.
South Arbuzovskoye Development
As previously announced, the initial well in the programme was the A-213 vertical well. This well discovered oil in the J1-2 interval for the first time at Arbuzovskoye. The well was initially produced in just the J1-2 interval. Since the previous update perforations were added to the J1-1 interval on 14 June. The combined production from the J1-1 and J1-2 intervals in the well is now over 350 bopd which is well above the Company’s original expectation of an initial rate of 125 bopd.
As also previously announced, the first horizontal well in the programme was A-214. This well had a record net pay of 931 m for Licence 61. The well is producing approximately 750 bopd and demonstrating positive pressure characteristics.
The second horizontal well, A-215, was spudded on 21 May 2016 and has been successfully completed with a horizontal segment of 1,007 m in the Upper Jurassic J1-1 interval at a depth of approximately -2,457 to -2,475 m TVDSS. Based on log data it is estimated that 809 m of the horizontal section is effective net pay. The A-215 well was brought online on 24 June and the current flow rate is around 650 bopd. The well has cleaned up and is producing about 5% water. The intake pressure in the well is relatively stable, which indicates that additional production capacity may exist.
The pressure data from both the A-214 and A-215 horizontal wells indicates that the wells are pump constrained and could produce at a higher rate; however, the current plan is to keep producing in this mode and monitor the wells to optimiselong term production performance. This will lessen the decline rate in the horizontal wells.
The Arbuzovskoye well A-216 was spudded on 20 June 2016. Well A-216 is a deviated (vertical in the reservoir) production well located to the south of well A-213. The well was not in the original firm work programme but has been added based on the good results of the A-213, A-214 and A-215 wells. It provides an additional drainage point on the southern end of the structure and targets the J1-1 and J1-2 intervals as seen in the A-213 well. Core taking in the J1-1 and J1-2 intervals in the well will provide additional data on the reservoir as well as the oil water contact in the J1-2 sandstone. The results of this well should be available later this month.
Production
Current gross production from Licence 61 is about 3,500 bopd (1,750 bopd net to PetroNeft). This represents record production for the Licence area and has resulted from the good results of the initial three wells at Arbuzovskoye, despite the high decline rate encountered at Tungolskoye and the shut-in of the S-373 well for the summer months following the end of the winter road season. The production results thus far at South Arbuzovskoye confirm that while there is some decline, it is not of the magnitude of decline experienced at Tungolskoye. This is due to the excellent reservoir properties and the thickness of the reservoir at Arbuzovskoye as compared to Tungolskoye.
Sibkrayevskoye Development
The S-374 delineation well was spudded on 3 July 2016. This is a delineation well on the southern portion of the field designed to further de-risk the development and move P3 to P2 reserves. All of the necessary studies and approvals are being completed in order to commence development of Sibkrayevskoye in Q1 2017.